Lockup stage and painting.

We finally have our missing awning window and brickwork is finished so are at the lockup stage…. finally.  Also painted too – cool.  Reasonably happy with the paintwork.  They didn’t do much sanding though.

The concrete slab has finally been fixed inside after sacking Cornell’s Concreting.  Porter Davis got a new guy in to grind back the rectification work that Cornells ‘tried’ to do and then fix it properly.  We now have a mostly level slab inside – good enough to lay the tiles on anyway.  What a saga – the slab was laid in February and fixed in August.  5 long months!

We are still waiting for the exterior of the slab to be fixed – sigh!!

 

 